Bulldozers begin preparing the new parking lot in front of the church. In the background, the parish center starts to receive its roof trusses.
Roof trusses go up around the hall. When complete, the trusses will hide HVAC equipment to be located on the roof.
Workers begin laying cement on the parish hall floor.
The parish hall received its floor this week.
Progress on the site includes the roof trusses, new concrete in the hall, and steel wall studs around the hall (not shown)
The new parish hall floor.
The new parish hall floor as viewed from Farragut St.
Progress continues on the new parish center. In the background are the formidable spires of St. Stan's.
Workers begin preparing the old high school site to become a parking lot.
Parking lot work continues.
Bulldozers prepare the new parking lot.
Bulldozers remove the concrete from the old bank building that stood on the corner of 22nd and Van Buren in the 40's.