Framing for the exterior walls of the office area went up this week. Here you can make out the windows on the west side of the building.
The north exterior wall of the office area is framed in.
Peeking through the corner of the hall towards the office area. Plywood was added to the roof of the hall this week.
The south wall of the office area, near the rectory. The windows in this area will contain the stained glass from the Blessed Angela Room.
The ceiling joists await installation.
Clearing of the site of the old high school is now complete. The next step will be to add drainage tile and prepare the lot for paving.
Clearing of the old high school site is now complete. The next step will be to install drainage tile
With the site now cleared, the full face of the church is now visible from Van Buren St and beyond.