FIRST STILE TO REPLACE BY DINTON ROAD FOVANT FP2 c dMacd
DONALD & DAVID P START DEMOLITION
STILE GONE, HOLE DIGGING WELL UNDERWAY c. dMacd
KISSING GATE IN PLACE
READY FOR CONCRETING IN
DAVID P LOOKING PLEASED, PETER? NOT SO SURE
FINAL JOB, MAKE GOOD BARB WIRE FENCE c dMacd
THE FINISHED JOB
MEANWHILE AT THE OTHER END OF FOVANT FP2 DAVID W DEMOLISHES ANOTHER OLD STILE
SIZING UP TO DIG THE HOLES
TOP OF THE HILL, NORMAN & DAVID W CHECK THE LEVELS
HOLES DUG & READY FOR CONCRETING IN
SOMEONE HAS TO FETCH WATER DAVID, FROM THE BOTTOM OF THE HILL
JOB ALMOST FINISHED
A CLOUD PASSES OVER FOVANT BADGES
COMPLETE AT THE JUNCTION OF FOVANT FPS 2 & 3
LUNCHTIME, AND BOTH KISSING GATES FINISHED
AFTER LUNCH CLEARANCE WORK ON FOVANT FP1
WHAT A MESS
GETTING BETTER
JOB ABOUT COMPLETED
TIME TO GO HOME NORMAN