South gable end with windows framed into SIPs
East side with overhang complete
North facing gable end
Foam expansion joint
Living shade tubes inserted into SIP splines
Roof 90% completed
Eagle Ridge Span feet
Prep'd panel to be lifted by crane
Five Eagle Ridge Spans to support upper roof - ICFs installed by others
Five Eagle Ridge Span trusses installed and braced
The crane swings 24 ft long prep'd panel
The panel is stapled underneath by the installers as the crane operator holds it in the air
The crane holds the elevated panel while the professional installers staple the underneath proir to the installation
While one installer stablizes the panel the other staples the underneath splines
The panel is set by the crane
24' x 12' jumbo panels are set in place with the use of a crane
Lloyd takes an important call
Onsite modifications needed as panel thicknesses differ
Panel was slid up the hip and small gaps get filled with two part foam to create airtight seal
Panel comes up short - we added a piece of lumber along the spline and the smaller gap gets filled with two part foam
Foam gap by design on top of Eagle Ridge Spans
Lower 10.25" panels rest on ICF and structural steel wall & 8.25" panels rest on Eagle Ridge Spans
SIP tape preinstalled on joints that bears on the Eagle Ridge Spans
Recycle center
Eagle Ridge Spans span 65' - 8"
Small gap in roof panel is repaired