Lot at 1021 Longfied Court, Halcyon Summit
typical exterior footing section
starting to pour foundations
foundations being poured
Preparation for slab pour. The metal keyway, which is used to control cracks while curing, is in and the anchor bolts to support steel columns, are being set.
Pumping concrete for slab. See how the elevator pit wall forms have remained in order to let the slab sit on top of the pre-poured elevator pit walls.
Setting structural steel for front porch. This will also support 2nd floor walls and roof.
2nd floor decking
Continue 2nd floor decking at elevator shaft
tongue and groove decking resting on engineered I-joists that are attached to laminated wood beams with joist hangers
preparation for and pumping of 2nd floor lightweight slab
setting grade pins and final check of wall layout (note: walls are bearing on floor deck and concrete is being poured 1.5" thick on a moisture barrier and up against the wall plates)
pour partially completed
concrete being pumped and partially complete
2nd floor walls up and roof trusses beginning to be set (note: opening at corner of buiding for steel stairs to be dropped into by the crane later that day, also the steel framing for the balcony is being welded)
trusses being set, see the 2nd floor walls sitting on the front porch structural steel
Structurally framed attic storage. There are steel stairs next to the CE rooms that lead to this area over the 2nd floor hallway.
Newly framed CE Rooms
Started laying brick
The E.I.F.S subcontractor followed the brick mason around the building, with the stryofoam. The final delivery of sheetrock was also being delivered
After the brick was laid, the mortar wash subcontractor followed the EIFS subcontractor around the building again
The EIFS subcontractor finished the color on top and then added the trim around the first floor windows. Parking lot is about to begin.