7/1/09 Reflections The building construction is over and inspections by the County are in progress and about 80% are done
7/1/09 As required by Lee County, the invasive species from the Preserves are being removed and treated to prevent future growth
6/29/09 See the reflection in the water
6/29/09 Reflections
6/24/09 The construction is over. County inspections in progress
6/7/09 Meeting of Executive Committee and Board of trustees held at the Temple building. Members are admiring the finished work and planning for next steps. Also learning how the controls and systems work.
6/10/09 Restroom fittings are in place
6/10/09 Mailbox installed
6/10/09 View of Temple with mailbox
6/10/09 the number '12552' installed
6/10/09 Sign at the entrance
6/9/09 Gate for west entrance installed
6/9/09 Gate for north breezeway installed
6/9/09 North breezeway Gate
6/9/09 Men's bathroom-picture1
6/9/09 Men's bathroom-picture2
6/9/09 Men's bathroom-picture3
6/9/09 West entrance gate, from inside
6/9/09 South breezeway gate
6/9/09 South Breezeway Gate
6/9/09 Ladies restroom - grabbar being installed
6/9/09 Ladies restroom - partitions being installed
6/9/09 Feet washing area
6/9/09 Mop Sink room
6/9/09
6/9/09 Sink inside temple area, with backsplash installed today
6/6/09 View from north side of Plantation Road
6/6/09 Waiting for Embarq connection -scheduled for 6/18/09
6/6/09 Front Gate
6/6/09 Lush Lawns
6/6/09 South side of FPL easement
6/5/09
6/5/09 2nd Fl room above rest rooms
6/5/09 Hydroseeding the open area along Plantation Road
6/5/09 Hydroseeding the open area on the west side
6/3/2009 Temple sign - it is on both sides of this monument, visible to those coming into Plantation Road either from south or from north side.
6/3/09 Temple sign
6/3/09 inside of building getting the finishing touches
6/3/09 During the week of 6/1/09, the A/C, Electrical, Plumbing, Fire Sprinkler, Fire Alarm, and plumbing inspections have been scheduled.
6/3/09 We have already applied for the Certificate of Completion, after taking care of all the requirements in terms of Utilties, Landscaping and Site development
6/3/09 Once the building related inspections are passed, we can ask for the Certificate of Occupancy
6/3/09 The cleaning crew is cleaning the floors
6/3/09
6/3/09 The remaining bathroom fixtures, the gates, and some tiling finishes are expected to be complete by 6/5/09